Refinery – Coffeyville, KS

Remove the tube bundle of 120 psig steam generator.  This was a “Red Line” (high priority) job, which was completed during an unplanned turnaround at the refinery. 

Taylor crews worked 24 hours a day for seven (7) days until the work was completed.  Safety was a major factor, and the project was completed on time, with no safety incidents and to the client’s satisfaction.

  • Installation of (2) towers was required to support Taylor’s beam and skating tools, which were necessary 
    to remove tube bundle 80 feet “off grade”
  • Utilize 140 ton truck crane to lift and lower the 72K lb. tube bundle

Transported the tube bundle to a repair facility in Houston, TX

 

Demag Main
COMPRESOR REPAIR

Refinery-Coffeyville, KS

Disassemble, clean, test where necessary and re-assemble three stages of a five-stage 37,000 HP compressor unit and cryogenic air separation plant. This included all piping, heads, pumps, tube bundles, shrouds and filters. The project was completed on time, with no safety incidents and to the client’s complete satisfaction.

  1. Lock out/tag out of water cooling system, compressor and electrical system
  2. Removal of inter-stage cooling system bolts and overhead piping
  1. Removal of 11 ton air cooler tube bundles
  2. Cleaning and refurbishing of air cooler coils
  3. Pressure checking tube bundles for leaks
  4. Reinstallation of air cooler tube bundles with crane
  5. Removal of panel from inlet air filter to access first stage of compressor
  6. Removal, checking and reinstallation of main compressor inlet guide vanes
  7. Removal and reinstallation of diffuser shroud inserts on main compressor

 

Jack
ENGINE BLOCK

Kansas

In order for our client to remove the crankshaft of this large stationary natural gas compressor engine, TCR utilized its gantry system to jack the top power cylinder engine block (approximately 130,000 lbs).

“The engine has 4 large compressor cylinders on each side that are driven by the engine.  Located at a gas compressor station in Kansas, this engine is used to move natural gas up a pipeline to the northeastern part of our country. Using Taylor crane to pick up the top frame off engines saves our customers time and money. The other option is to remove the roof from the building and have a large crane come in and pick up the engine frame.”

Mechanic Work On
FIRE TRUCKS

Coffeyville Fire Department, KS

Disassemble, clean, test where necessary and re-assemble three stages of a five-stage 37,000 HP compressor unit and cryogenic air separation plant. This included all piping, heads, pumps, tube bundles, shrouds and filters. The project was completed on time, with no safety incidents and to the client’s complete satisfaction.

  1. Lock out/tag out of water cooling system, compressor and electrical system
  2. Removal of inter-stage cooling system bolts and overhead piping

Bridge Crane
RELOCATION

Relocated Bridge Crane (overhead crane) from one bay to another, utilizing jacking system and turntable. Lifted, rotated, and lowered bridge crane and then traveled to next bay and reversed procedure for installation.

Dimensions: 76 ft. span, 60,000 lbs., 25 ft. off floor/grade.

CONVEYER
Assembly

Botanic Tonics – Santa Monica, CA

Taylor Crane & Rigging supplied supervision, manpower and equipment to assemble the conveyer as directed, and clean up after the job is done. The project was completed on time, with no incidents or injuries to the customer’s satisfaction.

OVERHEAD CRANE
Wheels Replacement

Wise Choice Crane & Controls – Port of Catoosa, OK

Taylor Crane & Rigging delivered comprehensive supervision, skilled manpower, and cutting-edge equipment for the seamless replacement of wheels on a 15-ton overhead crane. Our team expertly rotated and lowered the 93 foot span overhead crane, utilizing a robust 600-ton jacking system and turntable. With a strong commitment to punctuality and safety, the project was successfully completed on time, and to the customer satisfaction.

Related
PROJECTS

9

Transformer Switch over Mezzanine

Taylor moved (2) transformers on Mezzanine above chrome plating dip tanks. The transformers had to be switched. The first one weighed 1000# and the second one weighed 1700#..

9

Ball Mill Tire Change Out

Southern Welding contracted TCR to change out two 15′-diameter, 31,000-lb. tires and the adjacent rings (also 15′ in diameter) at the Central Plains Cement plant in Tulsa, OK..

9

Feed Water Heater Changeout

Taylor Crane & Rigging was challenged with removing two 115,000-lb. vessels and reinstalling two new replacement vessels from the second story of a power generation station ..

9

Plant Equipment Installation- New Plant

Supplied Manpower & equipment for Turnkey Installation of:

  • Over 40 Niagara clearing metal stamping presses
  • 22 Orttech Hydraulic units
  • 12 Sesco stock feeding systems…
9

Rear Modular Assembly Installation

Taylor Crane was awarded the contract from Forie Automation for the rear modular assembly project at the Woodbridge assembly plant in KC, MO. This project consisted of installation of the following:..

9

Sutton Table Removal & Relocation

Lower, remove, and relocate sutton tables and straightener.  Taylor provided manpower, equipment and materials necessary to modify the in-board and out-board table tops and drive bases for the straightener. 

VISIT US

Coffeyville, KS - Tulsa, OK

CALL US

(620) 251 - 1530

SEND US E-MAIL

tcr@taylorcrane.com

© 2024 TAYLOR CRANE & RIGGING
DCAD DESIGN