Millwright

TCR has a highly trained and well equipped millwright group who handles all your needs concerning fabrication. With fork trucks to 80,000 lbs and craning ability to 265 tons, our millwrights can disassemble and reassemble the largest presses, tube bundles and machines with ease. We can mobilize quickly and excel in the event of an emergency. 

Barrel Horse
INSTALLATION

Foundry – Pryor, Oklahoma

  • Remove existing steel support, conveyor, & conveyor frame
  • Receive and install new system (same as above)
  • 16 working days

Tube Bundle
CHANGE-OUT

Refinery – Coffeyville, KS

Remove the tube bundle of 120 psig steam generator.  This was a “Red Line” (high priority) job, which was completed during an unplanned turnaround at the refinery. 

Taylor crews worked 24 hours a day for seven (7) days until the work was completed.  Safety was a major factor, and the project was completed on time, with no safety incidents and to the client’s satisfaction.

  • Installation of (2) towers was required to support Taylor’s beam and skating tools, which were necessary 
    to remove tube bundle 80 feet “off grade”
  • Utilize 140 ton truck crane to lift and lower the 72K lb. tube bundle

Transported the tube bundle to a repair facility in Houston, TX

 

Generator
INSTALL

Cherokee Data Center – Tulsa, OK

  • 140 Ton crane and special rigging to offload the model 3612 generators from rail cars
  • Trucks and heavy-haul trailers to transport 10 miles across Tulsa
  • 80,000 lbs. capacity fork truck, 1” steel plate and skates to move in and place generators
  • Positioned the generators on elevated concrete foundations
  • Mounted isolator pads once each generator was raised to elevation
  • Lowered generators to sit on the isolators and holes marked for the HIT HY 150 Injection Adhesive anchor bolts
  • Raised generator to place skates under the generator, allowing anchor holes to be drilled and anchors set on each side
  • Lowered each generator down onto the 32 anchor bolts
  • All anchor bolts torqued to Caterpillar specifications
  • Set cooling units, mufflers and support tower air compressors and air receivers for the air starters, expansion joints for intake and exhaust piping

Bridge Crane
RELOCATION

Relocated Bridge Crane (overhead crane) from one bay to another, utilizing jacking system and turntable. Lifted, rotated, and lowered bridge crane and then traveled to next bay and reversed procedure for installation.

Dimensions: 76 ft. span, 60,000 lbs., 25 ft. off floor/grade.

Rear Modular Assembly
INSTALLATION

Fori – Kansas City, MO

Taylor Crane was awarded the contract from Forie Automation for the rear modular assembly project at the Woodbridge assembly plant in KC, MO. This project consisted of installation of the following:

  • Gorbel overhead bridge assemblies with tooling
  • Floor mounted jib booms/tooling
  • Articulating arms w/ tooling
  • Floor mounted conveyors – leveled and lined with-in .005 of 1 in.
  • Elevators and lowerators
  • Rear module aligners
  • (2) Rowboats for uploading conveyors
  • (2) auto torque stations
  • All safety cages and light curtain
  • All utility piping and air lines
  • All cable trey and wiring

This project was completed on time, under budget, with zero accidents.

Related
PROJECTS

9

Bridge Crane Relocation

Relocated Bridge Crane (overhead crane) from one bay to another, utilizing jacking system and turntable..

9

Rear Modular Assembly Installation

Taylor Crane was awarded the contract from Forie Automation for the rear modular assembly project at the Woodbridge assembly plant in KC, MO...

9

Generator Install

  • 140 Ton crane and special rigging to offload the model 3612 generators from rail cars
  • Trucks and heavy-haul trailers to transport 10 miles across Tulsa
9

Sutton Table Removal & Relocation

Lower, remove, and relocate sutton tables and straightener.  Taylor provided manpower, equipment and materials necessary to modify the in-board and out-board table tops and drive bases for the straightener. …

9

Ball Mill Tire Change Out

Southern Welding contracted TCR to change out two 15′-diameter, 31,000-lb. tires and the adjacent rings (also 15′ in diameter) at the Central Plains Cement plant in Tulsa, OK.

..

9

Sutton Table Removal & Relocation

Lower, remove, and relocate sutton tables and straightener.  Taylor provided manpower, equipment and materials necessary to modify the in-board and out-board table tops and drive bases for the straightener. 

VISIT US

Coffeyville, KS - Tulsa, OK

CALL US

(620) 251 - 1530

SEND US E-MAIL

tcr@taylorcrane.com

© 2024 TAYLOR CRANE & RIGGING
DCAD DESIGN